Experience Profile :
- 50 MW+ Gas/Oil based Power/Cogen installed/under execution
- 400 MW+ Solar power plant installed/under execution
- 1500+ MW Diesel Generators installed/under execution
An excerpt of Key Projects in Nigeria in the last 12 years are as follows :
S/No |
Project / Order details |
Product |
Status |
1 |
Oando/Alausa, Lagos State Governor Office Power Project, Nigeria |
2 x 3.3 MW Jenbach GEG + 2 x 2.5 MVA DG + BOP |
Commissioned & Handed Over-Oct 2013 |
2 |
Shoreline / Lafarge Cement, GT based Power Project, Nigeria |
3 x 5.5 MW Solar Turbines + BOP |
Commissioned & Handed Over-May 2014 |
3 |
Geeta Plastics, GEG based Captive Power Plant, Nigeria |
1 x 1.89 MW GEG + BOP |
Commissioned in Apr 2014 |
4 |
Cadbury Nigeria PLC |
3 x 1.5MW |
Commissioned in April 2017 |
5 |
Reliance Chemicals Agbara |
1 x 1.5MW |
Commissioned in 2018 |
6 |
Kuker Farms Abeokuta |
2 x 0.5MW |
Commissioned in 2019 |
7 |
Powering Bayelsa Through Sustainable Partnership |
1 x 65MW |
|
8 |
Powering Sustainable Transit at NRC |
1 x 6MW |
|
3 x 5.5MW Shoreline -Nigeria
Tailor-Made Solutions
-
1
Site conditions diagnosed to propose main driver as Gas Turbine instead of Customer’s RFP for Gas Engines -
2
Gas turbine commissioned in system with heavy jerks -
3
Gas Turbine successfully synchronized with existing Gas Engines -
4
Commissioned May 2014
Alausa IPP (10.6 MW) EPC – Lagos






Tailor-Made Solutions
-
1
Uneven landscape with slope downward bending -
2
Instead of backfilling the natural slope was maintained by sloping roads and drainage system -
3
Used pre-fabricated modules to improve overall quality and reduce site installation time -
4
Commissioned & Handed Over-Oct 2013
1 x 1.89MW Geeta Plastics Nigeria


Tailor-Made Solutions
-
1
Given Plot size had limited available space -
2
Equipment fit by shifting radiator and cooling tower on the roof -
3
Used pre-fabricated modules to reduce site installation time and improve overall quality -
4
Commissioned April 2014
3 x 1.5MVA CADBURY, IKEJA
Tailor-Made Solutions
-
1
Cadbury Nigeria PLC -
2
Commissioned in April 2017
3.5 Mw with 2 x 1364 + 1 x 775 Kw Containerized
Gas Genset based Power Plant, for Sapio Utilities, Lagos.



25 Mw with 5 x 5000 Gas Genset
based Power Plant at Seghzi Power Plant



Substation Maintenance and Construction



Construction and Installation of Distribution Network



Cable sleeves installation along Lekki- Ikoyi bridge



Rehabilitation of classrooms with Toilets



Streetlights installation in Lekki Phase 1



Construction of Kolawole Lawson Street, with Street Lights



Powering Bayelsa Through Sustainable Partnership
In collaboration with the Bayelsa State Government, TIS Renewable Energy Limited is undertaking a 65MW gas power plant Public-Private Partnership (PPP) project at the Gbarantoro power hub. This state-of-the-art facility will provide reliable electricity to 5 local government areas and the state capital, harnessing the power of clean-burning natural gas.
Through this innovative PPP model, we’re committed to delivering sustainable energy solutions that drive economic growth and improve the quality of life for communities across Bayelsa State. With our expertise in gas power generation, we’re paving the way for a greener, more efficient energy future.
Powering Sustainable Transit
TIS Renewable Energy Limited has installed a cutting-edge 6MW gas-powered plant at the Nigerian Railway compound in Ebute-meta, Lagos. This turnkey solution generates electricity from clean-burning natural gas, promoting thermal efficiency and low emissions for the Lagos-Ibadan transit services.
As a pilot project, the plant demonstrates TIS Renewable Energy Limited’s commitment to sustainable energy solutions in Nigeria’s transportation sector. Through innovative gas power generation, we’re enabling eco-friendly rail operations while driving progress toward a greener future.